3R & ADA - S GATEWAY DRIVE

Description: 3R & ADA - S GATEWAY DRIVE

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera County
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 29
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles  .79      
Reduced Operating/Maintenance Cost        
Rehabilitated Lane Miles (miles)  .79      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Madera  
Design (PS&E) Phase
Madera  
Right of Way Phase
Madera  
Construction Phase
Madera Jose Aguilar (559) 661-5418   jeaguilar@cityofmadera.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$206 $0 $206
Non-bond Funding
Local**
$231 $0 $231
 
Total**** $437 $0 $437

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $0 $5 $0 $0 $4
Design(PS&E)
$15 $0 $15 $6 $6 $9
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$417 $0 $417 $205 $205 $212
 
Total* $437 $0 $437 $212 $212 $225

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/29/2010 

12/15/2010 
03/01/2011 

03/01/2011 
09/20/2011 

11/30/2011 
100  07/02/2012 

08/30/2012 
-9 

-9 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/03/2010 

01/30/2011 
03/01/2011 

03/01/2011 
09/30/2011 

12/30/2011 
100  08/06/2012 

02/28/2013 
-10 

-14 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/15/2011 

06/15/2011 
03/01/2011 

03/01/2011 
05/15/2012 

07/31/2012 
100  04/17/2013 

11/06/2013 
-11 

-15 
Begin Closeout Phase

End Closeout Phase
07/31/2011 

12/31/2011 
03/01/2011 

 
01/15/2013 

08/15/2013 
100  11/07/2013 

10/02/2014 
-10 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles .79
Reduced Operating/Maintenance Cost
Rehabilitated Lane Miles (miles) .79

Bond Funding Cost
Adopted:
$206,000
Current Approved:
$20,600
Actual Expenditures:
$102,602

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle