TAHOE CITY TRANSIT CENTER

Description: Construct transit center, including public parking, seating and bicycle/pedestrian access paths.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Tahoe City
Zip Code 96145
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase in Transit Ridership        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Placer County Department of Public Works Brian Stewart (530) 581-6216   bstewart@placer.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$226 $0 $226
Non-bond Funding
State/Federal*
$4,253 $0 $4,253
Local**
$2,863 $0 $2,863
 
Total**** $7,342 $0 $7,342

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$253 $0 $253 $253 $253 $0
Design(PS&E)
$581 $0 $581 $588 $588 $-7
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,508 $0 $6,508 $6,508 $6,508 $0
 
Total* $7,342 $0 $7,342 $7,349 $7,349 $-7

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/13/2010 

02/17/2012 
 

 
01/13/2010 

02/17/2012 
100  06/08/2010 

10/29/2012 
-5 

-8 
Begin Closeout Phase

End Closeout Phase
02/17/2012 

08/17/2012 
 

 
02/17/2012 

08/17/2012 
100  10/29/2012 

11/28/2012 
-8 

-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Transit Ridership

Bond Funding Cost
Adopted:
$226,000
Current Approved:
$226,000
Actual Expenditures:
$226,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle