TWO MEDIUM BUSES FOR EXPANSION OF ADA PARATRANSIT |
Description: Purchase (2) medium size, 22-foot, 9-passenger seat, gasoline fuel with one wheelchair tie-down buses.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Mateo |
Zip Code | 94070 |
Senate District |
08, 11 |
Assembly District | 12, 19, 21 |
Congressional District | 12, 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Intercity Rail Round Trips | ||
Increase in Transit Ridership |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
San Mateo County Transit District | Rebecca Arthur | 6505086368 | arthurr@samtrans.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$49 | $0 | $49 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $143 | $143 | ||||
Local** |
$166 | $-117 | $49 | ||||
Total**** | $215 | $26 | $241 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$215 | $26 | $241 | $172 | $172 | $69 | |
Total* | $215 | $26 | $241 | $172 | $172 | $69 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/20/2011 07/20/2014 |
|
01/20/2011 07/20/2014 |
100 | 09/14/2011 02/28/2012 |
-8 29 |
Begin Closeout Phase
End Closeout Phase |
07/21/2014 12/31/2014 |
|
07/21/2014 12/31/2014 |
100 | 03/01/2012 06/30/2013 |
29 18 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Intercity Rail Round Trips | ||
Increase in Transit Ridership |
Bond Funding Cost | |
---|---|
Adopted: |
$49,000 |
Current Approved: |
$49,000 |
Actual Expenditures: |
$22,692 |
Status as of December 31, 2023.