REPLACEMENT MINI-VANS

Description: Purchase (10) 17-foot, 3-seat passenger, gasoline fuel with two wheelchair tie-down replacement paratransit mini-vans.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Mateo
Zip Code 94070
 
Senate District
08, 11
Assembly District 12, 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase in System Reliability        
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
San Mateo County Transit District Christine Dunn 6505086328   dunnc@samtrans.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$100 $0 $100
Non-bond Funding
State/Federal*
$404 $0 $404
Local**
$100 $0 $100
 
Total**** $604 $0 $604

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$604 $0 $604 $469 $469 $135
 
Total* $604 $0 $604 $469 $469 $135

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/09/2011 

01/31/2013 
 

 
06/30/2012 

01/31/2013 
100  09/14/2011 

02/15/2012 
10 

12 
Begin Closeout Phase

End Closeout Phase
02/01/2013 

04/30/2013 
 

 
02/01/2013 

04/30/2013 
100  02/16/2012 

05/07/2013 
12 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliability
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$100,000
Current Approved:
$1,000,000
Actual Expenditures:
$46,875

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle