Description: Purchase (10) 17-foot, 3-seat passenger, gasoline fuel with two wheelchair tie-down replacement paratransit mini-vans.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Mateo |
Zip Code | 94070 |
Senate District |
08, 11 |
Assembly District | 12, 19, 21 |
Congressional District | 12, 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliability | ||
Reduced Operating/Maintenance Cost |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
San Mateo County Transit District | Christine Dunn | 6505086328 | dunnc@samtrans.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$100 | $0 | $100 | ||||
Non-bond Funding | |||||||
State/Federal* |
$404 | $0 | $404 | ||||
Local** |
$100 | $0 | $100 | ||||
Total**** | $604 | $0 | $604 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$604 | $0 | $604 | $469 | $469 | $135 | |
Total* | $604 | $0 | $604 | $469 | $469 | $135 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/09/2011 01/31/2013 |
|
06/30/2012 01/31/2013 |
100 | 09/14/2011 02/15/2012 |
10 12 |
Begin Closeout Phase
End Closeout Phase |
02/01/2013 04/30/2013 |
|
02/01/2013 04/30/2013 |
100 | 02/16/2012 05/07/2013 |
12 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliability | ||
Reduced Operating/Maintenance Cost |
Bond Funding Cost | |
---|---|
Adopted: |
$100,000 |
Current Approved: |
$1,000,000 |
Actual Expenditures: |
$46,875 |
Status as of December 31, 2023.