Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
2012 Slurry Seal |
Description: 2012 Slurry Seal
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Nevada |
City | Truckee |
Zip Code | 96161 |
Senate District |
01 |
Assembly District | 03 |
Congressional District | 04 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Town of Truckee | Becky Bucar | 530-582-2932 | bbucar@townoftruckee.com | |
Design (PS&E) Phase |
Town of Truckee | Becky Bucar | 530-582-2932 | bbucar@townoftruckee.com | |
Right of Way Phase |
Town of Truckee | Becky Bucar | 530-582-2932 | bbucar@townoftruckee.com | |
Construction Phase |
Town of Truckee | Becky Bucar | 530-582-2932 | bbucar@townoftruckee.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$144 | $0 | $144 | ||||
Non-bond Funding | |||||||
Local** |
$681 | $0 | $681 | ||||
Total**** | $825 | $0 | $825 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$825 | $0 | $825 | $606 | $606 | $219 | |
Total* | $825 | $0 | $825 | $606 | $606 | $219 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2012 04/01/2012 |
10/06/2011 10/06/2011 |
02/01/2012 04/01/2012 |
100 | 02/01/2012 05/18/2012 |
0 -2 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/07/2012 09/30/2012 |
10/06/2011 10/06/2011 |
06/07/2012 09/30/2012 |
100 | 06/07/2012 09/14/2012 |
0 1 |
Begin Closeout Phase
End Closeout Phase |
11/01/2012 01/01/2013 |
10/06/2011 |
11/01/2012 01/01/2013 |
100 | 10/01/2012 01/01/2013 |
1 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$144,000 |
Current Approved: |
$144,000 |
Actual Expenditures: |
$144,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle