Caltrans Logo

CNG CONVERSION PROJECT (BUS PURCHASE)

Description: Santa Cruz County is replacing part of aging diesel transit fleet with 11 new natural-gas buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Cruz
City Aptos, Boulder Creek, Capitola, Davenport, Davenport/Santa Cruz, Felton, Santa Cruz, Scotts Valley, Watsonville
Zip Code 94020, 94060, 95003, 95005, 95006, 95007, 95010, 95017, 95018, 95019, 95033, 95037, 95039, 95041, 95060, 95062, 95064, 95065, 95066, 95073, 95076
 
Senate District
11, 15
Assembly District 27, 28
Congressional District 14, 17
 
Caltrans District
05
 
 
County/State Route Santa Cruz N/A
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Santa Cruz Metropolitan Transit District Ciro Aguirre 831-426-6080   caguirre@scmtd.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$427 $0 $427
Non-bond Funding
State/Federal*
$4,831 $0 $4,831
Local**
$562 $0 $562
 
Total**** $5,820 $0 $5,820

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,820 $0 $5,820 $5,721 $5,721 $99
 
Total* $5,820 $0 $5,820 $5,721 $5,721 $99

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/31/2011 

06/30/2012 
 

 
12/31/2011 

06/30/2012 
100  11/23/2011 

05/04/2012 


Begin Closeout Phase

End Closeout Phase
06/30/2012 

09/30/2012 
 

 
06/30/2012 

09/30/2012 
100  05/31/2012 

06/30/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions

Bond Funding Cost
Adopted:
$427,000
Current Approved:
$427,000
Actual Expenditures:
$427,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle