Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
10TH AVE WIDENING/RECONSTRUCTION PROJECT |
Description: Widening/Reconsruction - Third Street to Hanford-Armona Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kings |
City | Hanford |
Zip Code | 93230 |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 20 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (Mixed) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Design (PS&E) Phase |
City of Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Right of Way Phase |
City of Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Construction Phase |
City of Hanford | Lou Camara | (559) 585-2567 | lcamara@ci.hanford.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$750 | $0 | $750 | ||||
Non-bond Funding | |||||||
Local** |
$1,180 | $0 | $1,180 | ||||
Total**** | $1,930 | $0 | $1,930 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$20 | $0 | $20 | $20 | $20 | $0 | |
Design(PS&E) |
$100 | $0 | $100 | $100 | $100 | $0 | |
Right of Way |
$160 | $0 | $160 | $117 | $117 | $43 | |
Construction |
$1,650 | $0 | $1,650 | $1,989 | $1,989 | $-339 | |
Total* | $1,930 | $0 | $1,930 | $2,226 | $2,226 | $-296 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2011 01/01/2012 |
|
10/01/2011 01/01/2012 |
100 | 01/01/2012 04/23/2012 |
-3 -4 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2011 06/01/2012 |
|
10/01/2011 06/01/2012 |
100 | 03/01/2012 01/02/2014 |
-5 -19 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2012 06/01/2012 |
|
01/01/2012 06/01/2012 |
100 | 04/01/2012 10/30/2013 |
-3 -17 |
Begin Construction Phase
End Construction Phase |
09/01/2012 12/01/2012 |
|
09/01/2012 12/01/2012 |
100 | 02/04/2014 09/24/2014 |
-17 -22 |
Begin Closeout Phase
End Closeout Phase |
01/01/2013 02/01/2013 |
|
01/01/2013 02/01/2013 |
100 | 09/24/2014 10/20/2014 |
-21 -21 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (Mixed) |
Bond Funding Cost | |
---|---|
Adopted: |
$750,000 |
Current Approved: |
$750,000 |
Actual Expenditures: |
$750,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle