LOS OSOS VALLEY RD PROJECT |
Description: Widen Los Osos Road from Bush Street to Broderson Ave
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | Los Osos |
Zip Code | 93402 |
Senate District |
15 |
Assembly District | 33 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (Mixed) | ||
Separated Bike/Pedestrian Paths |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
San Luis Obispo County Department of Public Works | Genaro Diaz | 805-781-5279 | gdiaz@co.slo.ca.us | |
Design (PS&E) Phase |
San Luis Obispo County Department of Public Works | Genaro Diaz | 805-781-5279 | gdiaz@co.slo.ca.us | |
Right of Way Phase |
San Luis Obispo County Department of Public Works | Genaro Diaz | 805-781-5279 | gdiaz@co.slo.ca.us | |
Construction Phase |
San Luis Obispo County Department of Public Works | Genaro Diaz | 805-781-5279 | gdiaz@co.slo.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$300 | $-126 | $174 | ||||
Non-bond Funding | |||||||
Local** |
$400 | $-226 | $174 | ||||
Total**** | $700 | $-352 | $348 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$100 | $-100 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$600 | $-252 | $348 | $233 | $233 | $115 | |
Total* | $700 | $-352 | $348 | $233 | $233 | $115 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/31/2011 |
|
12/31/2011 |
100 | 01/23/2012 09/24/2012 |
0 -9 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/31/2011 |
|
12/31/2011 |
100 | 03/05/2012 02/19/2013 |
0 -14 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 02/19/2013 05/02/2013 |
0 0 |
Begin Construction Phase
End Construction Phase |
01/24/2012 12/31/2012 |
|
01/24/2012 12/31/2012 |
100 | 09/24/2013 02/04/2014 |
-20 -13 |
Begin Closeout Phase
End Closeout Phase |
01/01/2013 06/01/2013 |
|
01/01/2013 06/01/2013 |
100 | 02/05/2014 05/20/2014 |
-13 -12 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (Mixed) | ||
Separated Bike/Pedestrian Paths |
Bond Funding Cost | |
---|---|
Adopted: |
$300,000 |
Current Approved: |
$174,000 |
Actual Expenditures: |
$116,467 |
Status as of December 31, 2023.