LOS OSOS VALLEY RD PROJECT

Description: Widen Los Osos Road from Bush Street to Broderson Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City Los Osos
Zip Code 93402
 
Senate District
15
Assembly District 33
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Lane Miles Added (Mixed)        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
San Luis Obispo County Department of Public Works Genaro Diaz 805-781-5279   gdiaz@co.slo.ca.us
Design (PS&E) Phase
San Luis Obispo County Department of Public Works Genaro Diaz 805-781-5279   gdiaz@co.slo.ca.us
Right of Way Phase
San Luis Obispo County Department of Public Works Genaro Diaz 805-781-5279   gdiaz@co.slo.ca.us
Construction Phase
San Luis Obispo County Department of Public Works Genaro Diaz 805-781-5279   gdiaz@co.slo.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$300 $-126 $174
Non-bond Funding
Local**
$400 $-226 $174
 
Total**** $700 $-352 $348

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$100 $-100 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$600 $-252 $348 $233 $233 $115
 
Total* $700 $-352 $348 $233 $233 $115

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

12/31/2011 
 

 
 

12/31/2011 
100  01/23/2012 

09/24/2012 


-9 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

12/31/2011 
 

 
 

12/31/2011 
100  03/05/2012 

02/19/2013 


-14 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  02/19/2013 

05/02/2013 


Begin Construction Phase

End Construction Phase
01/24/2012 

12/31/2012 
 

 
01/24/2012 

12/31/2012 
100  09/24/2013 

02/04/2014 
-20 

-13 
Begin Closeout Phase

End Closeout Phase
01/01/2013 

06/01/2013 
 

 
01/01/2013 

06/01/2013 
100  02/05/2014 

05/20/2014 
-13 

-12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Lane Miles Added (Mixed)
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$300,000
Current Approved:
$174,000
Actual Expenditures:
$116,467

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle