NICOLAUS ROAD WIDENING |
Description: Widen Nicolaus Road from Aviation Blvd/Nelson Lane to Airport Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Placer |
City | Lincoln |
Zip Code | 95648 |
Senate District |
04 |
Assembly District | 06 |
Congressional District | 04 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (Mixed) | ||
Reduced Emissions |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Lincoln | Ray Leftwich | 916-434-2457 | rleftwich@ci.lincoln.ca.us | |
Design (PS&E) Phase |
City of Lincoln | Ray Leftwich | 916-434-2457 | rleftwich@ci.lincoln.ca.us | |
Right of Way Phase |
City of Lincoln | Ray Leftwich | 916-434-2457 | rleftwich@ci.lincoln.ca.us | |
Construction Phase |
City of Lincoln | Ray Leftwich | 916-434-2457 | rleftwich@ci.lincoln.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$758 | $0 | $758 | ||||
Non-bond Funding | |||||||
Local** |
$820 | $138 | $958 | ||||
Total**** | $1,578 | $138 | $1,716 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$10 | $-2 | $8 | $8 | $8 | $0 | |
Design(PS&E) |
$52 | $140 | $192 | $191 | $191 | $1 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,516 | $0 | $1,516 | $1,449 | $1,449 | $67 | |
Total* | $1,578 | $138 | $1,716 | $1,648 | $1,648 | $68 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2011 01/01/2012 |
|
10/01/2011 01/01/2012 |
100 | 10/01/2011 05/30/2012 |
0 -5 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2012 03/01/2012 |
|
01/01/2012 03/01/2012 |
100 | 01/01/2012 05/30/2012 |
0 -3 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2012 10/01/2012 |
|
05/01/2012 10/01/2012 |
100 | 08/01/2012 04/30/2013 |
-3 -7 |
Begin Closeout Phase
End Closeout Phase |
10/01/2012 12/01/2012 |
|
10/01/2012 12/01/2012 |
100 | 04/30/2013 07/31/2013 |
-7 -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Lane Miles Added (Mixed) | ||
Reduced Emissions |
Bond Funding Cost | |
---|---|
Adopted: |
$758,000 |
Current Approved: |
$758,000 |
Actual Expenditures: |
$724,576 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle