PLEASANT VALLEY/PATTERSON DRIVE SIGNALIZATION |
Description: Signalize the intersection of Pleasant Valley Road and Patterson Drive
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
El Dorado |
City | |
Zip Code | |
Senate District |
01 |
Assembly District | 04, 10 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | El Dorado 49 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
|||||
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$600 | $0 | $600 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,000 | $0 | $1,000 | ||||
Local** |
$2,298 | $0 | $2,298 | ||||
Total**** | $3,898 | $0 | $3,898 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$372 | $0 | $372 | $366 | $0 | $372 | |
Design(PS&E) |
$626 | $0 | $626 | $949 | $0 | $626 | |
Right of Way |
$700 | $0 | $700 | $721 | $749 | $-49 | |
Construction |
$2,200 | $0 | $2,200 | $2,772 | $0 | $2,200 | |
Total* | $3,898 | $0 | $3,898 | $4,807 | $749 | $3,149 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | 05/01/2007 04/17/2009 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2012 |
|
08/01/2012 |
100 | 04/17/2009 10/31/2013 |
0 -15 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2011 08/01/2012 |
|
07/01/2011 08/01/2012 |
100 | 07/01/2011 10/31/2013 |
0 -15 |
Begin Construction Phase
End Construction Phase |
12/01/2012 10/15/2013 |
|
12/01/2012 10/15/2013 |
100 | 10/03/2013 04/28/2015 |
-10 -19 |
Begin Closeout Phase
End Closeout Phase |
12/01/2013 04/01/2014 |
|
12/01/2013 04/01/2014 |
100 | 04/29/2015 12/31/2018 |
-17 -58 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput |
Bond Funding Cost | |
---|---|
Adopted: |
$600,000 |
Current Approved: |
$600,000 |
Actual Expenditures: |
$600,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle