PLEASANT VALLEY/PATTERSON DRIVE SIGNALIZATION

Description: Signalize the intersection of Pleasant Valley Road and Patterson Drive

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City
Zip Code
 
Senate District
01
Assembly District 04, 10
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 49
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$600 $0 $600
Non-bond Funding
State/Federal*
$1,000 $0 $1,000
Local**
$2,298 $0 $2,298
 
Total**** $3,898 $0 $3,898

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$372 $0 $372 $366 $0 $372
Design(PS&E)
$626 $0 $626 $949 $0 $626
Right of Way
$700 $0 $700 $721 $749 $-49
Construction
$2,200 $0 $2,200 $2,772 $0 $2,200
 
Total* $3,898 $0 $3,898 $4,807 $749 $3,149

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100  05/01/2007 

04/17/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

08/01/2012 
 

 
 

08/01/2012 
100  04/17/2009 

10/31/2013 


-15 
Begin Right of Way Phase

End Right of Way Phase
07/01/2011 

08/01/2012 
 

 
07/01/2011 

08/01/2012 
100  07/01/2011 

10/31/2013 


-15 
Begin Construction Phase

End Construction Phase
12/01/2012 

10/15/2013 
 

 
12/01/2012 

10/15/2013 
100  10/03/2013 

04/28/2015 
-10 

-19 
Begin Closeout Phase

End Closeout Phase
12/01/2013 

04/01/2014 
 

 
12/01/2013 

04/01/2014 
100  04/29/2015 

12/31/2018 
-17 

-58 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput

Bond Funding Cost
Adopted:
$600,000
Current Approved:
$600,000
Actual Expenditures:
$600,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle