Caltrans Logo

4TH ST - PINE TO K ST

Description: Rehab, resurface and reconstruct the city streets and improve drainage

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code
 
Senate District
12
Assembly District 29
Congressional District 19
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Madera Jose Aguilar 559-661-5418   jeaguilar@cityofmadera.com
Design (PS&E) Phase
City of Madera Jose Aguilar 559-661-5418   jeaguilar@cityofmadera.com
Right of Way Phase
City of Madera Jose Aguilar 559-661-5418   jeaguilar@cityofmadera.com
Construction Phase
City of Madera Jose Aguilar 559-661-5418   jeaguilar@cityofmadera.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$567 $0 $567
Non-bond Funding
Local**
$945 $0 $945
 
Total**** $1,512 $0 $1,512

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $0 $5 $5 $5 $0
Design(PS&E)
$117 $0 $117 $112 $112 $5
Right of Way
$30 $0 $30 $30 $30 $0
Construction
$1,360 $0 $1,360 $1,442 $1,442 $-82
 
Total* $1,512 $0 $1,512 $1,589 $1,589 $-77

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2009 

01/01/2010 
 

 
07/01/2009 

01/01/2010 
100  07/01/2009 

08/06/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2009 

08/30/2012 
 

 
10/01/2009 

08/30/2012 
100  10/01/2009 

02/28/2013 


-6 
Begin Right of Way Phase

End Right of Way Phase
02/01/2011 

09/01/2012 
 

 
02/01/2011 

09/01/2012 
100  02/01/2011 

09/01/2012 


Begin Construction Phase

End Construction Phase
02/20/2013 

07/30/2013 
 

 
02/20/2013 

07/30/2013 
100  05/15/2013 

02/05/2014 
-3 

-6 
Begin Closeout Phase

End Closeout Phase
06/30/2013 

08/30/2013 
 

 
06/30/2013 

08/30/2013 
100  02/06/2014 

04/14/2014 
-7 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$567,000
Current Approved:
$567,000
Actual Expenditures:
$566,984

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle