LAGUNA NIGUEL/MISSION VIEJO METROLINK

Description: METROLINK PARKING LOT EXPANSION

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Laguna Niguel
Zip Code
 
Senate District
33
Assembly District 73
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Increase in Intercity Rail Round Trips        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Orange County Transportation Authority (OCTA) Lora Cross 714-560-5788   lcross@octa.net
Design (PS&E) Phase
OCTA Lora Cross 714-560-5788   lcross@octa.net
Right of Way Phase
OCTA Lora Cross 714-560-5788   lcross@octa.net
Construction Phase
OCTA Lora Cross 714-560-5788   lcross@octa.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$695 $0 $695
Non-bond Funding
Local**
$3,437 $30 $3,467
 
Total**** $4,132 $30 $4,162

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$50 $0 $50 $68 $68 $-18
Right of Way
$2,613 $0 $2,613 $2,613 $2,613 $0
Construction
$1,469 $30 $1,499 $1,499 $1,499 $0
 
Total* $4,132 $30 $4,162 $4,180 $4,180 $-18

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2007 

12/03/2007 
 

 
09/01/2007 

12/03/2007 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/10/2012 

08/31/2012 
 

 
04/10/2012 

08/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
01/01/2008 

06/09/2008 
 

 
01/01/2008 

06/09/2008 
100   

 


Begin Construction Phase

End Construction Phase
12/27/2012 

04/17/2013 
 

 
12/27/2012 

04/17/2013 
100  01/28/2013 

10/28/2013 
-1 

-6 
Begin Closeout Phase

End Closeout Phase
04/17/2013 

06/17/2013 
 

 
04/17/2013 

06/17/2013 
100  10/29/2013 

04/01/2014 
-6 

-10 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Intercity Rail Round Trips

Bond Funding Cost
Adopted:
$695,000
Current Approved:
$695,000
Actual Expenditures:
$695,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle