Caltrans Logo

2013 SLURRY SEAL PROJECT

Description: Annual Slurry Seal

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada
City Truckee
Zip Code 96161
 
Senate District
01
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Town of Truckee Becky Bucar 530-582-2932   bbucar@townoftruckee.com
Design (PS&E) Phase
Town of Truckee Becky Bucar 530-582-2932   bbucar@townoftruckee.com
Right of Way Phase
 
Construction Phase
Town of Truckee Becky Bucar 530-582-2932   bbucar@townoftruckee.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$71 $0 $71
Non-bond Funding
Local**
$589 $0 $589
 
Total**** $660 $0 $660

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$660 $0 $660 $735 $735 $-75
 
Total* $660 $0 $660 $735 $735 $-75

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2013 

05/01/2013 
 

 
03/01/2013 

05/01/2013 
100  03/01/2013 

05/01/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2013 

08/15/2013 
 

 
06/01/2013 

08/15/2013 
100  06/18/2013 

09/24/2013 
-1 

-1 
Begin Closeout Phase

End Closeout Phase
10/15/2013 

12/15/2013 
 

 
10/15/2013 

12/15/2013 
100  10/15/2013 

11/07/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$71,000
Current Approved:
$71,000
Actual Expenditures:
$71,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle