LAKE AVENUE IMPROVEMENTS

Description: REPLACE AND REHAB EXISTING PAVEMENT WITH RUBBERIZED HOT MIX ASPHALT

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City Calipatria
Zip Code 92233
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
The Holt Group Justina Arce 760-337-3883   justina@theholtgroup.net
Design (PS&E) Phase
The Holt Group Justina Arce 760-337-3883   justina@theholtgroup.net
Right of Way Phase
TBD TBD TBD   TBD
Construction Phase
City of Calipatria Romualdo Medina 760-348-4141   rj_medina@calipatria.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$133 $0 $133
Non-bond Funding
Local**
$138 $11 $149
 
Total**** $271 $11 $282

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$271 $11 $282 $282 $282 $0
 
Total* $271 $11 $282 $282 $282 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2012 

02/01/2013 
 

 
10/01/2012 

02/01/2013 
100  10/01/2012 

07/26/2013 


-6 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2012 

03/01/2013 
 

 
12/01/2012 

03/01/2013 
100  12/01/2012 

04/04/2013 


-1 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2013 

11/01/2013 
 

 
06/01/2013 

11/01/2013 
100  06/11/2013 

09/27/2013 


Begin Closeout Phase

End Closeout Phase
12/01/2013 

12/30/2013 
 

 
12/01/2013 

12/30/2013 
100  09/28/2013 

12/29/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$133,000
Current Approved:
$133,000
Actual Expenditures:
$133,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle