WILLOUGHBY ROAD RESURFACE

Description: Road Rehabilitation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City
Zip Code
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Imperial County Public Works John Gay 760-482-4462   johngay@co.imperial.ca.us
Design (PS&E) Phase
Imperial County Public Works John Gay 760-482-4462   johngay@co.imperial.ca.us
Right of Way Phase
Imperial County Public Works John Gay 760-482-4462   johngay@co.imperial.ca.us
Construction Phase
Imperial County Public Works John Gay 760-482-4462   johngay@co.imperial.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$650 $0 $650
Non-bond Funding
Local**
$650 $0 $650
 
Total**** $1,300 $0 $1,300

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,300 $0 $1,300 $1,013 $1,013 $287
 
Total* $1,300 $0 $1,300 $1,013 $1,013 $287

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/15/2012 

11/05/2012 
 

 
09/15/2012 

11/05/2012 
100  08/01/2012 

08/20/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/18/2012 

12/31/2012 
 

 
07/18/2012 

12/31/2012 
100  07/18/2012 

05/15/2013 


-4 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2013 

04/01/2014 
 

 
11/01/2013 

04/01/2014 
100  08/13/2013 

04/15/2014 


Begin Closeout Phase

End Closeout Phase
06/01/2014 

07/01/2014 
 

 
06/01/2014 

07/01/2014 
100  04/16/2014 

05/08/2015 


-10 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$650,000
Current Approved:
$650,000
Actual Expenditures:
$424,944

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle