Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
DOGWOOD ROAD RESURFACE |
Description: Resurface Dogwood Road
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Imperial |
City | |
Zip Code | |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 51 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Imperial County Public Works | John Gay | 760-482-4462 | johngay@co.imperial.ca.us | |
Design (PS&E) Phase |
Imperial County Public Works | John Gay | 760-482-4462 | johngay@co.imperial.ca.us | |
Right of Way Phase |
Imperial County Public Works | John Gay | 760-482-4462 | johngay@co.imperial.ca.us | |
Construction Phase |
Imperial County Public Works | John Gay | 760-482-4462 | johngay@co.imperial.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$901 | $0 | $901 | ||||
Non-bond Funding | |||||||
Local** |
$901 | $0 | $901 | ||||
Total**** | $1,802 | $0 | $1,802 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,802 | $0 | $1,802 | $1,345 | $1,345 | $457 | |
Total* | $1,802 | $0 | $1,802 | $1,345 | $1,345 | $457 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/15/2012 11/05/2012 |
|
09/15/2012 11/05/2012 |
100 | 08/01/2012 08/20/2012 |
1 3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/18/2012 12/31/2012 |
|
07/18/2012 12/31/2012 |
100 | 07/18/2012 05/15/2013 |
0 -4 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
11/01/2013 04/01/2014 |
|
11/01/2013 04/01/2014 |
100 | 08/13/2013 06/20/2014 |
3 -3 |
Begin Closeout Phase
End Closeout Phase |
06/01/2014 07/01/2014 |
|
06/01/2014 07/01/2014 |
100 | 06/21/2014 04/07/2015 |
-1 -9 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$901,000 |
Current Approved: |
$901,000 |
Actual Expenditures: |
$574,440 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle