5TH STREET REPAVING

Description: Street Rehab

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Imperial
City Calexico
Zip Code 92231
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Calexico Lilliana Falomir 760-768-2160   falomirl@calexico.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$515 $0 $515
Non-bond Funding
Local**
$515 $0 $515
 
Total**** $1,030 $0 $1,030

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,030 $0 $1,030 $599 $599 $431
 
Total* $1,030 $0 $1,030 $599 $599 $431

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2012 

10/05/2012 
 

 
09/01/2012 

10/05/2012 
100  09/01/2012 

12/31/2013 


-15 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

01/15/2013 
 

 
11/01/2012 

01/15/2013 
100  01/02/2014 

02/14/2014 
-14 

-13 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2013 

12/01/2013 
 

 
09/01/2013 

12/01/2013 
100  03/28/2014 

01/20/2015 
-7 

-14 
Begin Closeout Phase

End Closeout Phase
12/15/2013 

01/30/2014 
 

 
12/15/2013 

01/30/2014 
100  01/21/2015 

07/08/2015 
-13 

-17 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$515,000
Current Approved:
$515,000
Actual Expenditures:
$299,744

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle