ALISO CREEK RD REHAB

Description: Rehab Aliso Creek Rd from Enterprise to Pacific Park Drive

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Aliso Viejo
Zip Code 92656
 
Senate District
33
Assembly District 70, 73
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Aliso Viejo Shaun Pelletier 949-425-2533   spelletier@cityofalisoviejo.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$318 $0 $318
Non-bond Funding
Local**
$425 $0 $425
 
Total**** $743 $0 $743

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$52 $0 $52 $57 $57 $-5
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$691 $0 $691 $517 $517 $174
 
Total* $743 $0 $743 $574 $574 $169

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

09/01/2012 
 

 
 

09/01/2012 
100  09/01/2012 

09/01/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

09/01/2012 
 

 
07/01/2012 

09/01/2012 
100  07/02/2012 

12/21/2012 


-4 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/03/2013 

09/18/2013 
 

 
07/03/2013 

09/18/2013 
100  08/21/2013 

10/29/2013 
-2 

-1 
Begin Closeout Phase

End Closeout Phase
09/19/2013 

11/01/2013 
 

 
09/19/2013 

11/01/2013 
100  10/30/2013 

03/27/2014 
-1 

-5 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$318,000
Current Approved:
$318,000
Actual Expenditures:
$258,457

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle