CERRITOS AVE E. WIDENING

Description: Widen Cerritos Ave from Walker St. to Angela Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Cypress
Zip Code 90630
 
Senate District
35
Assembly District 67
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
Cypress Kamran Dadbeh, P.E. 714-229-6740   kdadbeh@ci.cypress.ca.us
Right of Way Phase
 
Construction Phase
Cypress Kamran Dadbeh, P.E. 714-229-6740   kdadbeh@ci.cypress.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$168 $0 $168
Non-bond Funding
Local**
$271 $0 $271
 
Total**** $439 $0 $439

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$61 $0 $61 $70 $70 $-9
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$378 $0 $378 $345 $345 $33
 
Total* $439 $0 $439 $415 $415 $24

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/06/2012 

12/31/2012 
 

 
08/06/2012 

12/31/2012 
100  08/06/2012 

12/31/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/27/2012 

12/31/2012 
 

 
02/27/2012 

12/31/2012 
100  02/27/2012 

11/13/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/25/2013 

08/16/2013 
 

 
02/25/2013 

08/16/2013 
100  05/05/2013 

11/30/2016 
-2 

-40 
Begin Closeout Phase

End Closeout Phase
08/19/2013 

10/18/2013 
 

 
08/19/2013 

10/18/2013 
100  12/01/2016 

12/01/2017 
-40 

-50 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$168,000
Current Approved:
$168,000
Actual Expenditures:
$128,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle