CERRITOS AVE E. WIDENING |
Description: Widen Cerritos Ave from Walker St. to Angela Ave
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Cypress |
Zip Code | 90630 |
Senate District |
35 |
Assembly District | 67 |
Congressional District | 40 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Separated Bike/Pedestrian Paths |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
Cypress | Kamran Dadbeh, P.E. | 714-229-6740 | kdadbeh@ci.cypress.ca.us | |
Right of Way Phase |
|||||
Construction Phase |
Cypress | Kamran Dadbeh, P.E. | 714-229-6740 | kdadbeh@ci.cypress.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$168 | $0 | $168 | ||||
Non-bond Funding | |||||||
Local** |
$271 | $0 | $271 | ||||
Total**** | $439 | $0 | $439 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$61 | $0 | $61 | $70 | $70 | $-9 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$378 | $0 | $378 | $345 | $345 | $33 | |
Total* | $439 | $0 | $439 | $415 | $415 | $24 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/06/2012 12/31/2012 |
|
08/06/2012 12/31/2012 |
100 | 08/06/2012 12/31/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/27/2012 12/31/2012 |
|
02/27/2012 12/31/2012 |
100 | 02/27/2012 11/13/2012 |
0 2 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/25/2013 08/16/2013 |
|
02/25/2013 08/16/2013 |
100 | 05/05/2013 11/30/2016 |
-2 -40 |
Begin Closeout Phase
End Closeout Phase |
08/19/2013 10/18/2013 |
|
08/19/2013 10/18/2013 |
100 | 12/01/2016 12/01/2017 |
-40 -50 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Separated Bike/Pedestrian Paths |
Bond Funding Cost | |
---|---|
Adopted: |
$168,000 |
Current Approved: |
$168,000 |
Actual Expenditures: |
$128,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle