LAMBERT RD PHASE 2 REHAB

Description: Rehab Lambert Rd from Tamarack Ave to State College Blvd

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Brea
Zip Code 92821
 
Senate District
29
Assembly District 72
Congressional District 42
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Increase in System Reliability        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Brea Raul Lising 714-671-4450   raull@cityofbrea.net
Design (PS&E) Phase
City of Brea Raul Lising 714-671-4450   raull@cityofbrea.net
Right of Way Phase
 
Construction Phase
City of Brea Raul Lising 714-671-4450   raull@cityofbrea.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$362 $0 $362
Non-bond Funding
Local**
$432 $0 $432
 
Total**** $794 $0 $794

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2 $0 $2 $3 $3 $-1
Design(PS&E)
$68 $0 $68 $78 $78 $-10
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$724 $0 $724 $1,674 $1,674 $-950
 
Total* $794 $0 $794 $1,755 $1,755 $-961

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

07/15/2012 
 

 
07/01/2012 

07/15/2012 
100  07/01/2012 

10/19/2012 


-3 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

11/30/2012 
 

 
07/01/2012 

11/30/2012 
100  12/19/2012 

07/12/2013 
-6 

-7 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2013 

06/30/2014 
 

 
09/30/2013 

06/30/2014 
100  08/20/2013 

06/03/2014 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

10/30/2014 
 

 
07/01/2014 

10/30/2014 
100  06/04/2014 

01/13/2015 


-2 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliability
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$362,000
Current Approved:
$362,000
Actual Expenditures:
$362,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle