LOCAL ROAD REHAB

Description: Rehab Garden Grove Blvd

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Garden Grove
Zip Code
 
Senate District
34
Assembly District 68, 69
Congressional District 47
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Garden Grove Digna De Los Reyes 714-741-5179   dignar@ci.garden-grove.ca.us
Design (PS&E) Phase
City of Garden Grove Digna De Los Reyes 714-741-5179   dignar@ci.garden-grove.ca.us
Right of Way Phase
City of Garden Grove Digna De Los Reyes 714-741-5179   dignar@ci.garden-grove.ca.us
Construction Phase
City of Garden Grove Digna De Los Reyes 714-741-5179   dignar@ci.garden-grove.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$842 $0 $842
Non-bond Funding
Local**
$842 $0 $842
 
Total**** $1,684 $0 $1,684

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,684 $0 $1,684 $2,331 $2,331 $-647
 
Total* $1,684 $0 $1,684 $2,331 $2,331 $-647

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

08/30/2012 
 

 
 

08/30/2012 
100  08/30/2012 

08/30/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2012 

12/31/2012 
 

 
03/01/2012 

12/31/2012 
100  04/01/2012 

03/30/2013 
-1 

-3 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/31/2013 

01/31/2014 
 

 
07/31/2013 

01/31/2014 
100  08/13/2013 

07/10/2014 


-5 
Begin Closeout Phase

End Closeout Phase
02/01/2014 

06/30/2014 
 

 
02/01/2014 

06/30/2014 
25  07/11/2014 

01/08/2015 
-5 

-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$842,000
Current Approved:
$842,000
Actual Expenditures:
$842,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle