MAGNOLIA AVE RECONSTRUCTION

Description: Reconstruct Magnolia Ave from Orangethorpe Ave to Ash Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Fullerton
Zip Code 92833
 
Senate District
33
Assembly District 72
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fullerton Vincent Oseguera 714.738.6851   vincento@ci.fullerton.ca.us
Design (PS&E) Phase
City of Fullerton Vincent Oseguera 714.738.6851   vincento@ci.fullerton.ca.us
Right of Way Phase
City of Fullerton Vincent Oseguera 714.738.6851   vincento@ci.fullerton.ca.us
Construction Phase
City of Fullerton Vincent Oseguera 714.738.6851   vincento@ci.fullerton.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$410 $0 $410
Non-bond Funding
Local**
$820 $0 $820
 
Total**** $1,230 $0 $1,230

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$100 $0 $100 $85 $85 $15
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,130 $0 $1,130 $1,427 $1,427 $-297
 
Total* $1,230 $0 $1,230 $1,512 $1,512 $-282

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2011 

10/01/2012 
 

 
08/01/2011 

10/01/2012 
100  08/01/2011 

08/09/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2011 

12/01/2012 
 

 
08/01/2011 

12/01/2012 
100  08/01/2011 

03/21/2013 


-4 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/16/2013 

10/01/2013 
 

 
04/16/2013 

10/01/2013 
100  05/21/2013 

11/15/2013 
-1 

-1 
Begin Closeout Phase

End Closeout Phase
11/01/2013 

12/01/2013 
 

 
11/01/2013 

12/01/2013 
100  11/16/2013 

07/22/2014 


-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$410,000
Current Approved:
$410,000
Actual Expenditures:
$410,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle