Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
MAGNOLIA AVE RECONSTRUCTION |
Description: Reconstruct Magnolia Ave from Orangethorpe Ave to Ash Ave
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Fullerton |
Zip Code | 92833 |
Senate District |
33 |
Assembly District | 72 |
Congressional District | 40 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Fullerton | Vincent Oseguera | 714.738.6851 | vincento@ci.fullerton.ca.us | |
Design (PS&E) Phase |
City of Fullerton | Vincent Oseguera | 714.738.6851 | vincento@ci.fullerton.ca.us | |
Right of Way Phase |
City of Fullerton | Vincent Oseguera | 714.738.6851 | vincento@ci.fullerton.ca.us | |
Construction Phase |
City of Fullerton | Vincent Oseguera | 714.738.6851 | vincento@ci.fullerton.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$410 | $0 | $410 | ||||
Non-bond Funding | |||||||
Local** |
$820 | $0 | $820 | ||||
Total**** | $1,230 | $0 | $1,230 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$100 | $0 | $100 | $85 | $85 | $15 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,130 | $0 | $1,130 | $1,427 | $1,427 | $-297 | |
Total* | $1,230 | $0 | $1,230 | $1,512 | $1,512 | $-282 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
08/01/2011 10/01/2012 |
|
08/01/2011 10/01/2012 |
100 | 08/01/2011 08/09/2012 |
0 2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2011 12/01/2012 |
|
08/01/2011 12/01/2012 |
100 | 08/01/2011 03/21/2013 |
0 -4 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/16/2013 10/01/2013 |
|
04/16/2013 10/01/2013 |
100 | 05/21/2013 11/15/2013 |
-1 -1 |
Begin Closeout Phase
End Closeout Phase |
11/01/2013 12/01/2013 |
|
11/01/2013 12/01/2013 |
100 | 11/16/2013 07/22/2014 |
0 -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$410,000 |
Current Approved: |
$410,000 |
Actual Expenditures: |
$410,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle