LAKE FOREST & ROCKFIELD RESURFACE

Description: Resurface Lake Forest Drive and Rockfield Blvd

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Lake Forest
Zip Code 92630
 
Senate District
33
Assembly District 70
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Lake Forest Douglas A Erdman (949) 282-5233   derdman@lakeforestca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$479 $0 $479
Non-bond Funding
Local**
$556 $0 $556
 
Total**** $1,035 $0 $1,035

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,035 $0 $1,035 $869 $869 $166
 
Total* $1,035 $0 $1,035 $869 $869 $166

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2012 

05/15/2012 
 

 
05/01/2012 

05/15/2012 
100  05/01/2012 

05/15/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/15/2012 

07/31/2012 
 

 
05/15/2012 

07/31/2012 
100  05/15/2012 

07/31/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/31/2012 

02/27/2013 
 

 
12/31/2012 

02/27/2013 
100  07/29/2013 

11/19/2013 
-7 

-9 
Begin Closeout Phase

End Closeout Phase
03/01/2013 

04/30/2013 
 

 
03/01/2013 

04/30/2013 
100  11/20/2013 

04/21/2014 
-9 

-12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$479,000
Current Approved:
$479,000
Actual Expenditures:
$429,866

 

Status as of December 31, 2023.