SUNKIST STREET IMPROVEMENTS

Description: Improvements on Sunkist from Cerritos Ave to Tryon Ave.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Anaheim
Zip Code 92806
 
Senate District
33
Assembly District 69, 72
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
City of Anaheim Cesar Carrillo (714) 765-5473   CCarrillo@anaheim.net
Right of Way Phase
 
Construction Phase
City of Anaheim Robert Palaeologus (714) 765-5285   RPalaeologus@anaheim.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$835 $0 $835
Non-bond Funding
Local**
$835 $0 $835
 
Total**** $1,670 $0 $1,670

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,670 $0 $1,670 $1,697 $1,697 $-27
 
Total* $1,670 $0 $1,670 $1,697 $1,697 $-27

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2012 

07/01/2012 
 

 
06/01/2012 

07/01/2012 
06/01/2012 

07/01/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2008 

07/30/2012 
 

 
06/01/2008 

07/30/2012 
100  06/01/2008 

03/21/2013 


-8 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/18/2012 

12/01/2013 
 

 
12/18/2012 

12/01/2013 
100  04/30/2013 

01/21/2014 
-4 

-2 
Begin Closeout Phase

End Closeout Phase
12/01/2013 

03/01/2014 
 

 
12/01/2013 

03/01/2014 
100  01/22/2014 

06/26/2014 
-2 

-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$835,000
Current Approved:
$835,000
Actual Expenditures:
$835,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle