NEWPORT AVE BICYCLE TRAIL

Description: Remove and Replace existing asphalt concrete off-road bicycle trail with PCC trail

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Tustin
Zip Code 92780
 
Senate District
33
Assembly District 70
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Tustin Eric Johnson (714) 573-3320   ejohnson@tustinca.org
Design (PS&E) Phase
City of Tustin Eric Johnson (714) 573-3320   ejohnson@tustinca.org
Right of Way Phase
 
Construction Phase
City of Tustin Eric Johnson (714) 573-3320   ejohnson@tustinca.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$200 $0 $200
Non-bond Funding
Local**
$250 $0 $250
 
Total**** $450 $0 $450

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$50 $0 $50 $61 $61 $-11
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$400 $0 $400 $629 $629 $-229
 
Total* $450 $0 $450 $690 $690 $-240

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/02/2012 

08/31/2012 
 

 
07/02/2012 

08/31/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/02/2012 

11/30/2012 
 

 
07/02/2012 

11/30/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2013 

08/01/2013 
 

 
05/01/2013 

08/01/2013 
100  08/20/2013 

07/15/2014 
-4 

-12 
Begin Closeout Phase

End Closeout Phase
09/01/2013 

12/01/2013 
 

 
09/01/2013 

12/01/2013 
25  07/16/2014 

01/14/2015 
-11 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$200,000
Actual Expenditures:
$200,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle