BROOKHURST STREET IMPROVEMENTS |
Description: Improve Brookhurst from South City Limits to Mc Fadden Ave
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Westminster |
Zip Code | 92683 |
Senate District |
34 |
Assembly District | 67, 68 |
Congressional District | 40, 46 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Westminster | Art Bashmakian | (714) 548-3484 | abashmakian@westminster-ca.gov | |
Design (PS&E) Phase |
City of Westminster | Marwan Youssef | (714) 548-3460 | myoussef@westminster-ca.gov | |
Right of Way Phase |
|||||
Construction Phase |
City of Westminster | Marwan Youssef | (714) 548-3460 | myoussef@westminster-ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$520 | $0 | $520 | ||||
Non-bond Funding | |||||||
Local** |
$692 | $0 | $692 | ||||
Total**** | $1,212 | $0 | $1,212 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,212 | $0 | $1,212 | $1,221 | $1,221 | $-9 | |
Total* | $1,212 | $0 | $1,212 | $1,221 | $1,221 | $-9 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/12/2012 07/01/2012 |
|
05/12/2012 07/01/2012 |
100 | 05/12/2012 07/01/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2012 08/01/2012 |
|
05/01/2012 08/01/2012 |
100 | 05/01/2012 08/01/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/01/2013 11/30/2013 |
|
09/01/2013 11/30/2013 |
100 | 08/28/2013 04/09/2014 |
0 -4 |
Begin Closeout Phase
End Closeout Phase |
01/07/2014 02/01/2014 |
|
01/07/2014 02/01/2014 |
100 | 04/10/2014 09/16/2014 |
-3 -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle