STREET REHAB

Description: Removal and replacement of deteriorated pavement sections in multiple locations throughout the City of Villa Park.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Villa Park
Zip Code 92861
 
Senate District
33
Assembly District 60
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Villa Park Akram Hindiyeh 949-585-0477   akram@civil-source.com
Design (PS&E) Phase
City of Villa Park Akram Hindiyeh 949-585-0477   akram@civil-source.com
Right of Way Phase
City of Villa Park Akram Hindiyeh 949-585-0477   akram@civil-source.com
Construction Phase
City of Villa Park Akram Hindiyeh 949-585-0477   akram@civil-source.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$318 $-193 $125
Non-bond Funding
Local**
$358 $168 $526
 
Total**** $676 $-25 $651

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $-5 $0 $0 $0 $0
Design(PS&E)
$20 $-20 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$651 $0 $651 $858 $858 $-207
 
Total* $676 $-25 $651 $858 $858 $-207

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/30/2012 

08/30/2012 
 

 
07/30/2012 

08/30/2012 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/30/2012 

10/30/2012 
 

 
08/30/2012 

10/30/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/26/2013 

08/30/2013 
06/27/2013 

06/27/2013 
12/11/2013 

05/30/2014 
100  10/28/2013 

09/24/2014 


-4 
Begin Closeout Phase

End Closeout Phase
09/01/2013 

10/30/2013 
06/27/2013 

 
06/01/2014 

07/31/2014 
100  09/25/2014 

05/22/2017 
-4 

-34 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$318,000
Current Approved:
$125,000
Actual Expenditures:
$125,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle