Caltrans Logo

ARTERIAL & LOCAL ST REHAB

Description: Road resurfacing for Arterial and Local Streets within Seal Beach, CA.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Seal Beach
Zip Code 90740
 
Senate District
35
Assembly District 67
Congressional District 46
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Seal Beach David Spitz 562-431-2527 X1331   dspitz@sealbeachca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$318 $0 $318
Non-bond Funding
Local**
$337 $0 $337
 
Total**** $655 $0 $655

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$655 $0 $655 $682 $682 $-27
 
Total* $655 $0 $655 $682 $682 $-27

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

07/31/2012 
 

 
07/01/2012 

07/31/2012 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2012 

10/31/2012 
 

 
08/01/2012 

10/31/2012 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

09/30/2013 
 

 
07/01/2013 

09/30/2013 
100  06/03/2013 

08/12/2013 


Begin Closeout Phase

End Closeout Phase
10/01/2013 

12/31/2013 
 

 
10/01/2013 

12/31/2013 
100  08/13/2013 

12/10/2014 


-11 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$318,000
Current Approved:
$318,000
Actual Expenditures:
$318,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle