Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
JERONIMO RD RESURFACE |
Description: Road resurfacing from Los Alisos Blvd to Marguerite Pkwy.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Mission Viejo |
Zip Code | |
Senate District |
33 |
Assembly District | 71 |
Congressional District | 42 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Mission Viejo | Joe Ames | 949-470-8419 | james@cityofmissionviejo.org | |
Design (PS&E) Phase |
City of Mission Viejo | Joe Ames | 949-470-8419 | james@cityofmissionviejo.org | |
Right of Way Phase |
City of Mission Viejo | Joe Ames | 949-470-8419 | james@cityofmissionviejo.org | |
Construction Phase |
City of Mission Viejo | Joe Ames | 949-470-8419 | james@cityofmissionviejo.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$574 | $0 | $574 | ||||
Non-bond Funding | |||||||
Local** |
$804 | $0 | $804 | ||||
Total**** | $1,378 | $0 | $1,378 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$100 | $0 | $100 | $59 | $59 | $41 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,278 | $0 | $1,278 | $1,417 | $1,417 | $-139 | |
Total* | $1,378 | $0 | $1,378 | $1,476 | $1,476 | $-98 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/30/2012 |
|
12/30/2012 |
100 | 12/10/2012 |
0 1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2012 12/30/2012 |
|
09/30/2012 12/30/2012 |
100 | 09/30/2012 12/30/2012 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2013 12/30/2013 |
|
04/30/2013 12/30/2013 |
100 | 04/30/2013 12/02/2013 |
0 1 |
Begin Closeout Phase
End Closeout Phase |
01/01/2014 03/30/2014 |
|
01/01/2014 03/30/2014 |
100 | 12/03/2013 05/05/2014 |
1 -1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$574,000 |
Current Approved: |
$574,000 |
Actual Expenditures: |
$574,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle