JERONIMO RD RESURFACE

Description: Road resurfacing from Los Alisos Blvd to Marguerite Pkwy.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Mission Viejo
Zip Code
 
Senate District
33
Assembly District 71
Congressional District 42
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Mission Viejo Joe Ames 949-470-8419   james@cityofmissionviejo.org
Design (PS&E) Phase
City of Mission Viejo Joe Ames 949-470-8419   james@cityofmissionviejo.org
Right of Way Phase
City of Mission Viejo Joe Ames 949-470-8419   james@cityofmissionviejo.org
Construction Phase
City of Mission Viejo Joe Ames 949-470-8419   james@cityofmissionviejo.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$574 $0 $574
Non-bond Funding
Local**
$804 $0 $804
 
Total**** $1,378 $0 $1,378

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$100 $0 $100 $59 $59 $41
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,278 $0 $1,278 $1,417 $1,417 $-139
 
Total* $1,378 $0 $1,378 $1,476 $1,476 $-98

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

12/30/2012 
 

 
 

12/30/2012 
100   

12/10/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2012 

12/30/2012 
 

 
09/30/2012 

12/30/2012 
100  09/30/2012 

12/30/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2013 

12/30/2013 
 

 
04/30/2013 

12/30/2013 
100  04/30/2013 

12/02/2013 


Begin Closeout Phase

End Closeout Phase
01/01/2014 

03/30/2014 
 

 
01/01/2014 

03/30/2014 
100  12/03/2013 

05/05/2014 


-1 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$574,000
Current Approved:
$574,000
Actual Expenditures:
$574,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle