EL TORO RD REHAB

Description: Pavement rehab for El Toro Rd and Ridge Route Dr.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Laguna Hills
Zip Code 92653
 
Senate District
33
Assembly District 73
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Laguna Hills Kenneth Rosenfield 949-707-2655   krosenfield@ci.laguna-hills.ca.us
Design (PS&E) Phase
City of Laguna Hills Kenneth Rosenfield 949-707-2655   krosenfield@ci.laguna-hills.ca.us
Right of Way Phase
 
Construction Phase
City of Laguna Hills Kenneth Rosenfield 949-707-2655   krosenfield@ci.laguna-hills.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$343 $0 $343
Non-bond Funding
Local**
$937 $0 $937
 
Total**** $1,280 $0 $1,280

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,280 $0 $1,280 $1,048 $1,048 $232
 
Total* $1,280 $0 $1,280 $1,048 $1,048 $232

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

12/01/2012 
 

 
07/01/2012 

12/01/2012 
100  10/01/2012 

10/17/2012 
-3 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

12/01/2012 
 

 
07/01/2012 

12/01/2012 
100  07/01/2012 

04/30/2013 


-5 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

06/01/2014 
 

 
07/01/2013 

06/01/2014 
100  06/25/2013 

12/09/2014 


-6 
Begin Closeout Phase

End Closeout Phase
07/01/2014 

12/01/2014 
 

 
07/01/2014 

12/01/2014 
25  12/10/2014 

01/21/2015 
-5 

-2 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$343,000
Current Approved:
$343,000
Actual Expenditures:
$343,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle