ROSE DRIVE AND YORBA LINDA BLVD INTERSECTION |
Description: Improve Rose Drive and Yorba Linda Blvd
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Placentia |
Zip Code | 92870 |
Senate District |
29 |
Assembly District | 72 |
Congressional District | 40, 42 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Placentia | Michael McConaha | 714-993-8120 | mmcconaha@placentia.org | |
Design (PS&E) Phase |
City of Placentia | Michael McConaha | 714-993-8120 | mmcconaha@placentia.org | |
Right of Way Phase |
City of Placentia | Michael McConaha | 714-993-8120 | mmcconaha@placentia.org | |
Construction Phase |
City of Placentia | Michael McConaha | 714-993-8120 | mmcconaha@placentia.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$95 | $0 | $95 | ||||
Non-bond Funding | |||||||
Local** |
$95 | $0 | $95 | ||||
Private*** |
$110 | $0 | $110 | ||||
Total**** | $300 | $0 | $300 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$300 | $0 | $300 | $147 | $147 | $153 | |
Total* | $300 | $0 | $300 | $147 | $147 | $153 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2012 08/01/2012 |
|
07/01/2012 08/01/2012 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2012 08/31/2012 |
|
06/01/2012 08/31/2012 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/20/2013 06/03/2013 |
|
04/20/2013 06/03/2013 |
100 | 04/16/2013 11/01/2013 |
0 -5 |
Begin Closeout Phase
End Closeout Phase |
06/03/2013 06/30/2013 |
|
06/03/2013 06/30/2013 |
100 | 11/02/2013 05/01/2014 |
-5 -10 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$95,000 |
Current Approved: |
$95,000 |
Actual Expenditures: |
$73,711 |
Status as of December 31, 2023.