Caltrans Logo

VALENCIA AVE REHAB

Description: Rehab Valencia Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Placentia
Zip Code 92870
 
Senate District
29
Assembly District 72
Congressional District 40, 42
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Placentia Michael McConaha 714-993-8120   mmcconaha@placentia.org
Design (PS&E) Phase
City of Placentia Michael McConaha 714-993-8120   mmcconaha@placentia.org
Right of Way Phase
City of Placentia Michael McConaha 714-993-8120   mmcconaha@placentia.org
Construction Phase
City of Placentia Michael McConaha 714-993-8120   mmcconaha@placentia.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$318 $0 $318
Non-bond Funding
Local**
$318 $0 $318
 
Total**** $636 $0 $636

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$636 $0 $636 $642 $642 $-6
 
Total* $636 $0 $636 $642 $642 $-6

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/10/2012 

08/01/2012 
 

 
05/10/2012 

08/01/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2012 

08/31/2012 
 

 
06/01/2012 

08/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
04/20/2013 

06/03/2013 
 

 
04/20/2013 

06/03/2013 
100  05/07/2013 

11/05/2013 
-1 

-5 
Begin Closeout Phase

End Closeout Phase
06/03/2013 

06/30/2013 
 

 
06/03/2013 

06/30/2013 
100  11/05/2013 

05/01/2014 
-5 

-10 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$318,000
Current Approved:
$318,000
Actual Expenditures:
$318,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle