CAMINO DE LOS MARES REHAB

Description: Pavement rehab from Avenida Vaquero to Camino Vera Cruz.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City San Clemente
Zip Code 92672
 
Senate District
38
Assembly District 73
Congressional District 44
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of San Clemente Ben Parker 949-361-6138   parkerb@san-clemente.org
Design (PS&E) Phase
City of San Clemente Ben Parker 949-361-6138   parkerb@san-clemente.org
Right of Way Phase
City of San Clemente Ben Parker 949-361-6138   parkerb@san-clemente.org
Construction Phase
City of San Clemente Ben Parker 949-361-6138   parkerb@san-clemente.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$318 $0 $318
Non-bond Funding
Local**
$1,082 $0 $1,082
 
Total**** $1,400 $0 $1,400

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,400 $0 $1,400 $941 $941 $459
 
Total* $1,400 $0 $1,400 $941 $941 $459

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2012 

06/15/2012 
 

 
01/01/2012 

06/15/2012 
100  01/01/2012 

07/11/2012 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2011 

06/15/2012 
 

 
06/01/2011 

06/15/2012 
100  06/01/2011 

06/15/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/15/2013 

05/01/2013 
 

 
01/15/2013 

05/01/2013 
100  08/20/2013 

04/15/2014 
-7 

-12 
Begin Closeout Phase

End Closeout Phase
05/15/2013 

08/15/2013 
 

 
05/15/2013 

08/15/2013 
25  04/16/2014 

10/02/2014 
-11 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$318,000
Current Approved:
$318,000
Actual Expenditures:
$318,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle