IDAHO ST PAVEMENT REHAB

Description: Pavement rehab from Lambert Rd to Imperial Hwy.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City La Habra
Zip Code 90631
 
Senate District
29
Assembly District 55
Congressional District 39
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of La Habra Sam Makar 562-905-9652   samm@lahabracity.com
Design (PS&E) Phase
City of La Habra Sam Makar 562-905-9652   samm@lahabracity.com
Right of Way Phase
 
Construction Phase
City of La Habra Sam Makar 562-905-9652   samm@lahabracity.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$314 $-68 $246
Non-bond Funding
Local**
$314 $-68 $246
 
Total**** $628 $-136 $492

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$628 $-136 $492 $440 $440 $52
 
Total* $628 $-136 $492 $440 $440 $52

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

10/31/2012 
 

 
07/01/2012 

10/31/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

10/01/2012 
 

 
07/01/2012 

10/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2013 

07/01/2013 
 

 
03/01/2013 

07/01/2013 
100  03/18/2013 

07/01/2013 
-1 

Begin Closeout Phase

End Closeout Phase
07/01/2013 

09/01/2013 
 

 
07/01/2013 

09/01/2013 
100  07/02/2013 

09/11/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$314,000
Current Approved:
$246,000
Actual Expenditures:
$220,250

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle