Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
SANTA MARGARITA PRKWY REHAB (PHASE 1) |
Description: Pavement rehab from Avenida De Las Flores to Antonio Pkwy (Phase 1).
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange |
City | Rancho Santa Margarita |
Zip Code | |
Senate District |
33 |
Assembly District | 71 |
Congressional District | 42 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
City of Rancho Santa Margarita | Cindy Kwong | 949-635-1800X6506 | ckwong@cityofrsm.org | |
Right of Way Phase |
|||||
Construction Phase |
City of Rancho Santa Margarita | Cindy Kwong | 949-635-1800X6506 | ckwong@cityofrsm.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$99 | $0 | $99 | ||||
Non-bond Funding | |||||||
Local** |
$501 | $0 | $501 | ||||
Total**** | $600 | $0 | $600 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$65 | $0 | $65 | $34 | $34 | $31 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$535 | $0 | $535 | $399 | $399 | $136 | |
Total* | $600 | $0 | $600 | $432 | $432 | $168 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/01/2012 |
|
09/01/2012 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/19/2012 09/01/2012 |
|
01/19/2012 09/01/2012 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/14/2013 06/26/2013 |
|
03/14/2013 06/26/2013 |
100 | 04/10/2013 05/30/2013 |
-1 1 |
Begin Closeout Phase
End Closeout Phase |
09/19/2013 11/01/2013 |
|
09/19/2013 11/01/2013 |
100 | 05/30/2013 10/25/2013 |
4 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$99,000 |
Current Approved: |
$99,000 |
Actual Expenditures: |
$99,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle