SKYLINE DRIVE RECONSTRUCTION

Description: Reconstruction from Cowan Heights Dr to Apsley Rd.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City N/A
Zip Code
 
Senate District
33
Assembly District 71
Congressional District 45
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
County of Orange Joel Samonte 714-245-4558   joel.samonte@ocpw.ocgov.com
Right of Way Phase
 
Construction Phase
County of Orange Joel Samonte 714-245-4558   joel.samonte@ocpw.ocgov.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$252 $0 $252
Non-bond Funding
Local**
$328 $-16 $312
 
Total**** $580 $-16 $564

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$76 $-16 $60 $51 $51 $9
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$504 $0 $504 $606 $606 $-102
 
Total* $580 $-16 $564 $658 $658 $-94

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

03/29/2005 
 

 
 

03/29/2005 
100  10/04/2012 

12/04/2012 


-94 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2005 

11/01/2012 
 

 
03/01/2005 

11/01/2012 
100  10/16/2012 

12/19/2012 
-93 

-2 
Begin Right of Way Phase

End Right of Way Phase
 

01/07/2007 
 

 
 

01/07/2007 
 

 


Begin Construction Phase

End Construction Phase
10/01/2013 

12/01/2013 
 

 
10/01/2013 

12/01/2013 
100  05/21/2013 

12/03/2013 


Begin Closeout Phase

End Closeout Phase
12/01/2013 

06/01/2014 
 

 
12/01/2013 

06/01/2014 
100  12/04/2013 

03/18/2015 


-10 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$252,000
Current Approved:
$252,000
Actual Expenditures:
$252,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle