DALE STREET RECONSTRUCTION

Description: Reconstruction from Orange County Flood Control District Channel to Orangewood Ave.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City N/A
Zip Code
 
Senate District
34
Assembly District 68
Congressional District 47
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
County of Orange Joel Samonte 714-245-4558   joel.samonte@ocpw.ocgov.com
Right of Way Phase
 
Construction Phase
County of Orange Joel Samonte 714-245-4558   joel.samonte@ocpw.ocgov.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$158 $-51 $107
Non-bond Funding
Local**
$205 $-51 $154
 
Total**** $363 $-102 $261

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$47 $0 $47 $39 $39 $8
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$316 $-102 $214 $218 $218 $-4
 
Total* $363 $-102 $261 $257 $257 $4

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

08/01/2012 
 

 
07/01/2012 

08/01/2012 
100  05/21/2012 

12/04/2012 


-4 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/15/2012 

12/15/2012 
 

 
07/15/2012 

12/15/2012 
100  07/27/2012 

12/19/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2013 

12/01/2013 
 

 
09/01/2013 

12/01/2013 
100  05/21/2013 

10/10/2013 


Begin Closeout Phase

End Closeout Phase
01/01/2014 

02/01/2014 
 

 
01/01/2014 

02/01/2014 
25  10/11/2013 

02/25/2015 


-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$158,000
Current Approved:
$107,000
Actual Expenditures:
$107,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle