ACQUISITION OF ALTERNATE FUEL TROLLEYS

Description: Trolley bus aquisition.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Laguna Beach
Zip Code 92651
 
Senate District
35
Assembly District 70
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Increase in System Reliability        
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Laguna Beach Tom Toman 949 497-0303   TToman@lagunabeachcity.net
Design (PS&E) Phase
City of Laguna Beach Tom Toman 949 497-0303   TToman@lagunabeachcity.net
Right of Way Phase
 
Construction Phase
City of Laguna Beach Tom Toman 949 497-0303   TToman@lagunabeachcity.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$318 $0 $318
Non-bond Funding
Local**
$318 $0 $318
 
Total**** $636 $0 $636

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$636 $0 $636 $597 $597 $39
 
Total* $636 $0 $636 $597 $597 $39

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2012 

08/01/2012 
 

 
06/01/2012 

08/01/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2012 

08/01/2012 
 

 
01/01/2012 

08/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/06/2012 

07/01/2013 
 

 
12/06/2012 

07/01/2013 
100  06/18/2013 

09/09/2015 
-6 

-27 
Begin Closeout Phase

End Closeout Phase
08/01/2013 

11/01/2013 
 

 
08/01/2013 

11/01/2013 
100  09/10/2015 

12/21/2016 
-26 

-38 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliability
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$318,000
Current Approved:
$318,000
Actual Expenditures:
$298,589

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle