Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
PRESIDENTIAL STREET REHAB |
Description: Overlay several streets in the SW section of City of Chowchilla
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera |
City | Chowchilla |
Zip Code | 93610 |
Senate District |
14 |
Assembly District | 25 |
Congressional District | 19 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Chowchilla | Joanne Upton | (559) 665-8615 | jupton@ci.chowchilla.ca.us | |
Design (PS&E) Phase |
City of Chowchilla | Jaspreet Mangat | (559) 665-8615 | jmangat@ci.chowchilla.ca.us | |
Right of Way Phase |
City of Chowchilla | Joanne Upton | (559) 665-8615 | jupton@ci.chowchilla.ca.us | |
Construction Phase |
City of Chowchilla | Jaspreet Mangat | (559) 665-8615 | jmangat@ci.chowchilla.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$240 | $0 | $240 | ||||
Non-bond Funding | |||||||
Local** |
$287 | $0 | $287 | ||||
Total**** | $527 | $0 | $527 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$5 | $0 | $5 | $3 | $5 | $0 | |
Design(PS&E) |
$42 | $0 | $42 | $42 | $42 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$480 | $0 | $480 | $495 | $495 | $-15 | |
Total* | $527 | $0 | $527 | $540 | $542 | $-15 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2013 02/01/2013 |
|
01/01/2013 02/01/2013 |
100 | 04/15/2013 04/17/2013 |
-3 -2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2013 06/01/2013 |
|
02/01/2013 06/01/2013 |
100 | 08/01/2013 11/12/2013 |
-6 -5 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/01/2013 10/01/2013 |
|
08/01/2013 10/01/2013 |
100 | 12/10/2013 12/07/2014 |
-4 -14 |
Begin Closeout Phase
End Closeout Phase |
10/01/2013 12/01/2013 |
|
10/01/2013 12/01/2013 |
0 | 12/08/2014 03/03/2015 |
-14 -15 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$240,000 |
Current Approved: |
$240,000 |
Actual Expenditures: |
$240,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle