Caltrans Logo

HUMBOLDT & VICINITY REHAB PHASE I

Description: Pavement rehab, replacement of existing storm drain, and addition of new curb and gutter.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mendocino
City Willits
Zip Code
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Increase in System Reliability        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Willits Gary Pedroni (Contract Planner) (707) 459-7124   GPedroni@pmcworld.com
Design (PS&E) Phase
City of Willits Jeremy Ronco (707) 459-7154   JRonco@WillitsCity.com
Right of Way Phase
City of Willits Tom Mannatt (707) 459-7136   TMannatt@WillitsCity.com
Construction Phase
City of Willits Tom Mannatt (707) 459-7136   TMannatt@WillitsCity.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$116 $0 $116
Non-bond Funding
Local**
$596 $0 $596
 
Total**** $712 $0 $712

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$712 $0 $712 $486 $486 $226
 
Total* $712 $0 $712 $486 $486 $226

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

10/31/2013 
 

 
07/01/2013 

10/31/2013 
100  06/03/2013 

09/12/2013 


Begin Closeout Phase

End Closeout Phase
12/01/2013 

01/31/2014 
 

 
12/01/2013 

01/31/2014 
100  09/13/2013 

01/14/2014 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliability
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$116,000
Current Approved:
$116,000
Actual Expenditures:
$116,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle