BUSINESS AREA STREET IMPROVEMENT

Description: Business area street improvement on segments of Cerritos Ave, Las Vasqueros C, Hombolt St, and Reagan St.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Los Alamitos
Zip Code 90720
 
Senate District
35
Assembly District 67
Congressional District 40
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Los Alamitos David Hunt 562 431-3538   dhunt@cityoflosalamitos.org
Design (PS&E) Phase
City of Los Alamitos David Hunt 562 431-3538   dhunt@cityoflosalamitos.org
Right of Way Phase
City of Los Alamitos David Hunt 562 431-3538   dhunt@cityoflosalamitos.org
Construction Phase
City of Los Alamitos David Hunt 562 431-3538   dhunt@cityoflosalamitos.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$318 $0 $318
Non-bond Funding
Local**
$318 $0 $318
 
Total**** $636 $0 $636

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$636 $0 $636 $628 $628 $8
 
Total* $636 $0 $636 $628 $628 $8

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2012 

10/01/2012 
 

 
07/01/2012 

10/01/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2012 

10/12/2012 
 

 
07/01/2012 

10/12/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2013 

07/01/2013 
 

 
03/01/2013 

07/01/2013 
100  05/20/2013 

09/06/2013 
-3 

-2 
Begin Closeout Phase

End Closeout Phase
08/01/2013 

10/01/2013 
 

 
08/01/2013 

10/01/2013 
25  09/07/2013 

07/24/2015 
-1 

-22 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$318,000
Current Approved:
$318,000
Actual Expenditures:
$313,766

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle