NELSON LANE IMPROVEMENTS

Description: Widen Nelson Lane

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Lincoln
Zip Code 95648
 
Senate District
04
Assembly District 06
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Lincoln Ray Leftwich 916-434-2457   rleftwich@ci.lincoln.ca.us
Design (PS&E) Phase
City of Lincoln Ray Leftwich 916-434-2457   rleftwich@ci.lincoln.ca.us
Right of Way Phase
City of Lincoln Ray Leftwich 916-434-2457   rleftwich@ci.lincoln.ca.us
Construction Phase
City of Lincoln Ray Leftwich 916-434-2457   rleftwich@ci.lincoln.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$600 $0 $600
Non-bond Funding
State/Federal*
$0 $6,416 $6,416
Local**
$800 $1,225 $2,025
 
Total**** $1,400 $7,641 $9,041

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$30 $-30 $0 $0 $0 $0
Design(PS&E)
$70 $1,286 $1,356 $1,355 $1,355 $1
Right of Way
$100 $-100 $0 $0 $0 $0
Construction
$1,200 $6,485 $7,685 $6,583 $6,583 $1,102
 
Total* $1,400 $7,641 $9,041 $7,938 $7,938 $1,103

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/19/2011 

12/17/2012 
 

 
12/19/2011 

12/17/2012 
100  12/19/2011 

07/05/2013 


-7 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/12/2013 

03/12/2013 
 

 
02/12/2013 

03/12/2013 
100  05/01/2013 

12/27/2013 
-3 

-10 
Begin Right of Way Phase

End Right of Way Phase
02/12/2013 

03/12/2013 
 

 
02/12/2013 

03/12/2013 
100  05/01/2013 

12/24/2013 
-3 

-10 
Begin Construction Phase

End Construction Phase
04/12/2013 

10/30/2013 
 

 
04/12/2013 

10/30/2013 
100  04/10/2014 

03/10/2015 
-12 

-17 
Begin Closeout Phase

End Closeout Phase
10/30/2013 

12/30/2013 
 

 
10/30/2013 

12/30/2013 
100  03/11/2015 

11/06/2015 
-17 

-23 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$600,000
Current Approved:
$600,000
Actual Expenditures:
$600,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle