Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
WILLOW RD EXTENSION MITIGATION |
Description: Willow Road Extension/US 101 Interchange Project
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | Nipomo |
Zip Code | 93444 |
Senate District |
17 |
Assembly District | 35 |
Congressional District | 24 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | ||
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
San Luis Obispo County | Genaro Diaz | 805-781-5279 | gdiaz@co.slo.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$375 | $0 | $375 | ||||
Non-bond Funding | |||||||
Local** |
$375 | $0 | $375 | ||||
Total**** | $750 | $0 | $750 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$750 | $0 | $750 | $1,030 | $1,030 | $-280 | |
Total* | $750 | $0 | $750 | $1,030 | $1,030 | $-280 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/13/2003 12/01/2008 |
|
05/13/2003 12/01/2008 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2010 09/18/2012 |
|
06/01/2010 09/18/2012 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
11/15/2012 02/28/2013 |
|
11/15/2012 02/28/2013 |
100 | 03/19/2013 04/07/2017 |
-4 -50 |
Begin Closeout Phase
End Closeout Phase |
04/01/2013 07/15/2013 |
|
04/01/2013 07/15/2013 |
100 | 04/08/2017 11/01/2017 |
-49 -52 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | ||
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$375,000 |
Current Approved: |
$375,000 |
Actual Expenditures: |
$375,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle