Caltrans Logo

CAMPUS DR/UPRR CROSSING

Description: Extend Campus Drive from Sixth St to UPRR crossing

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Hanford
Zip Code 93230
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Hanford Lou Camara 5595852567   lcamara@ci.hanford.ca.us
Design (PS&E) Phase
City of Hanford Lou Camara 5595852567   lcamara@ci.hanford.ca.us
Right of Way Phase
City of Hanford Lou Camara 5595852567   lcamara@ci.hanford.ca.us
Construction Phase
City of Hanford Lou Camara 5595852567   lcamara@ci.hanford.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$320 $0 $320
Non-bond Funding
Local**
$420 $0 $420
 
Total**** $740 $0 $740

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$60 $0 $60 $55 $55 $5
Right of Way
$40 $0 $40 $21 $21 $19
Construction
$640 $0 $640 $751 $751 $-111
 
Total* $740 $0 $740 $827 $827 $-87

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

01/06/2009 
 

 
 

01/06/2009 
100  11/18/2008 

03/08/2013 


-51 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2012 

05/01/2013 
 

 
12/01/2012 

05/01/2013 
100  02/01/2013 

10/01/2013 
-2 

-5 
Begin Right of Way Phase

End Right of Way Phase
02/01/2013 

05/01/2013 
 

 
02/01/2013 

05/01/2013 
100  03/09/2013 

04/08/2013 
-1 

Begin Construction Phase

End Construction Phase
08/01/2013 

12/01/2013 
 

 
08/01/2013 

12/01/2013 
100  12/03/2013 

09/03/2014 
-4 

-9 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

02/01/2014 
 

 
01/01/2014 

02/01/2014 
100  09/04/2014 

01/09/2015 
-8 

-11 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)
Reduced Emissions

Bond Funding Cost
Adopted:
$320,000
Current Approved:
$320,000
Actual Expenditures:
$320,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle