Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
MONTE VISTA AVE WIDENING |
Description: Widen Monte Vista Ave from a two lane to three lane ave.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Montclair |
Zip Code | 91763 |
Senate District |
32 |
Assembly District | 61 |
Congressional District | 26 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Peak Period Time Savings (minutes) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Montclair | Michael C. Hudson | 909-625-9441 | mhudson@cityofmontclair.org | |
Design (PS&E) Phase |
City of Montclair | Michael C. Hudson | 909-625-9441 | mhudson@cityofmontclair.org | |
Right of Way Phase |
City of Montclair | Michael C. Hudson | 909-625-9444 | mhudson@cityofmontclair.org | |
Construction Phase |
City of Montclair | Michael C. Hudson | 909-625-9441 | mhudson@cityofmontclair.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$180 | $0 | $180 | ||||
Non-bond Funding | |||||||
Local** |
$483 | $0 | $483 | ||||
Total**** | $663 | $0 | $663 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$83 | $0 | $83 | $57 | $57 | $26 | |
Right of Way |
$220 | $0 | $220 | $4 | $4 | $216 | |
Construction |
$360 | $0 | $360 | $462 | $462 | $-102 | |
Total* | $663 | $0 | $663 | $523 | $523 | $140 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/01/2012 03/01/2013 |
|
12/01/2012 03/01/2013 |
100 | 11/19/2012 12/03/2012 |
0 3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2013 05/01/2013 |
|
03/01/2013 05/01/2013 |
100 | 11/19/2012 02/03/2014 |
3 -9 |
Begin Right of Way Phase
End Right of Way Phase |
05/01/2013 08/01/2013 |
|
05/01/2013 08/01/2013 |
100 | 01/29/2013 04/24/2013 |
3 3 |
Begin Construction Phase
End Construction Phase |
09/01/2013 02/01/2014 |
|
09/01/2013 02/01/2014 |
100 | 04/07/2014 09/29/2014 |
-7 -8 |
Begin Closeout Phase
End Closeout Phase |
02/01/2014 04/01/2014 |
|
02/01/2014 04/01/2014 |
100 | 09/30/2014 01/08/2015 |
-8 -9 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | ||
Peak Period Time Savings (minutes) |
Bond Funding Cost | |
---|---|
Adopted: |
$180,000 |
Current Approved: |
$180,000 |
Actual Expenditures: |
$180,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle