Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
STREET REHAB |
Description: Rehab various locations
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Bruno |
Zip Code | 94066 |
Senate District |
08 |
Assembly District | 19 |
Congressional District | 12 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of San Bruno | William Li | (650) 616-7069 | wli@sanbruno.ca.gov | |
Design (PS&E) Phase |
City of San Bruno | William Li | (650) 616-7069 | wli@sanbruno.ca.gov | |
Right of Way Phase |
City of San Bruno | William Li | (650) 616-7069 | wli@sanbruno.ca.gov | |
Construction Phase |
City of San Bruno | William Li | (650) 616-7069 | wli@sanbruno.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$431 | $0 | $431 | ||||
Non-bond Funding | |||||||
Local** |
$856 | $0 | $856 | ||||
Total**** | $1,287 | $0 | $1,287 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$40 | $0 | $40 | $27 | $27 | $13 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,247 | $0 | $1,247 | $1,471 | $1,471 | $-224 | |
Total* | $1,287 | $0 | $1,287 | $1,498 | $1,498 | $-211 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2012 03/01/2013 |
|
12/01/2012 03/01/2013 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/01/2012 01/15/2013 |
|
12/01/2012 01/15/2013 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/22/2013 09/25/2013 |
|
05/22/2013 09/25/2013 |
100 | 07/23/2013 07/08/2014 |
-2 -10 |
Begin Closeout Phase
End Closeout Phase |
09/26/2013 12/31/2013 |
|
09/26/2013 12/31/2013 |
100 | 07/09/2014 10/27/2017 |
-10 -47 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$431,000 |
Current Approved: |
$431,000 |
Actual Expenditures: |
$431,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle