STREET RESURFACING PROGRAM FY 12/13

Description: Improve various city streets

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City East Palo Alto
Zip Code 94303
 
Senate District
11
Assembly District 21
Congressional District 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of East Palo Alto Kamal Fallaha 650-853-3189   KFallaha@cityofepa.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$495 $0 $495
Non-bond Funding
Local**
$595 $0 $595
 
Total**** $1,090 $0 $1,090

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$100 $0 $100 $30 $30 $70
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$990 $0 $990 $912 $912 $78
 
Total* $1,090 $0 $1,090 $942 $942 $148

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2012 

01/01/2013 
 

 
12/01/2012 

01/01/2013 
100   

02/15/2013 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/15/2012 

03/31/2013 
 

 
12/15/2013 

02/15/2014 
100  01/22/2013 

02/28/2013 
11 

12 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  02/28/2013 

03/08/2013 


Begin Construction Phase

End Construction Phase
06/15/2013 

11/30/2013 
 

 
04/01/2013 

08/01/2013 
100  12/12/2013 

05/17/2016 
-8 

-34 
Begin Closeout Phase

End Closeout Phase
11/30/2013 

05/31/2014 
 

 
08/01/2013 

08/15/2013 
100  05/18/2016 

06/06/2017 
-34 

-46 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$495,000
Current Approved:
$495,000
Actual Expenditures:
$455,869

 

Status as of December 31, 2023.