STREET RESURFACING PROGRAM FY 12/13 |
Description: Improve various city streets
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | East Palo Alto |
Zip Code | 94303 |
Senate District |
11 |
Assembly District | 21 |
Congressional District | 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
City of East Palo Alto | Kamal Fallaha | 650-853-3189 | KFallaha@cityofepa.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$495 | $0 | $495 | ||||
Non-bond Funding | |||||||
Local** |
$595 | $0 | $595 | ||||
Total**** | $1,090 | $0 | $1,090 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$100 | $0 | $100 | $30 | $30 | $70 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$990 | $0 | $990 | $912 | $912 | $78 | |
Total* | $1,090 | $0 | $1,090 | $942 | $942 | $148 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/01/2012 01/01/2013 |
|
12/01/2012 01/01/2013 |
100 | 02/15/2013 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/15/2012 03/31/2013 |
|
12/15/2013 02/15/2014 |
100 | 01/22/2013 02/28/2013 |
11 12 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 02/28/2013 03/08/2013 |
0 0 |
Begin Construction Phase
End Construction Phase |
06/15/2013 11/30/2013 |
|
04/01/2013 08/01/2013 |
100 | 12/12/2013 05/17/2016 |
-8 -34 |
Begin Closeout Phase
End Closeout Phase |
11/30/2013 05/31/2014 |
|
08/01/2013 08/15/2013 |
100 | 05/18/2016 06/06/2017 |
-34 -46 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$495,000 |
Current Approved: |
$495,000 |
Actual Expenditures: |
$455,869 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle