STREET RESURFACING PROJECT

Description: Resurface Streets in Foster City

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City Foster City
Zip Code 94404
 
Senate District
08
Assembly District 19
Congressional District 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Foster City Ashraf Shah (650) 286-3588   ashah@fostercity.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$508 $0 $508
Non-bond Funding
Local**
$508 $0 $508
 
Total**** $1,016 $0 $1,016

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,016 $0 $1,016 $1,085 $1,085 $-69
 
Total* $1,016 $0 $1,016 $1,085 $1,085 $-69

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2012 

10/30/2012 
 

 
09/01/2012 

10/30/2012 
100  09/01/2012 

10/30/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2012 

12/01/2012 
 

 
10/01/2012 

12/01/2012 
100  10/01/2012 

12/01/2012 


Begin Right of Way Phase

End Right of Way Phase
09/01/2012 

09/30/2012 
 

 
09/01/2012 

09/30/2012 
100  09/01/2012 

09/30/2012 


Begin Construction Phase

End Construction Phase
05/01/2013 

10/30/2013 
 

 
05/01/2013 

10/30/2013 
100  03/18/2013 

12/16/2013 


-2 
Begin Closeout Phase

End Closeout Phase
11/01/2013 

12/30/2013 
 

 
11/01/2013 

12/30/2013 
100  12/17/2013 

03/19/2014 
-2 

-3 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$508,000
Current Approved:
$508,000
Actual Expenditures:
$508,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle