CITYWIDE STREET REHAB

Description: Rehab roadway

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Mateo
Zip Code
 
Senate District
08
Assembly District 19
Congressional District 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of San Mateo Otis Chan 650-522-7305   ochan@cityofsanmateo.org
Design (PS&E) Phase
City of San Mateo Otis Chan 650-522-7305   ochan@cityofsanmateo.org
Right of Way Phase
City of San Mateo Otis Chan 650-522-7305   ochan@cityofsanmateo.org
Construction Phase
City of San Mateo Otis Chan 650-522-7305   ochan@cityofsanmateo.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$613 $0 $613
Non-bond Funding
Local**
$668 $0 $668
 
Total**** $1,280 $0 $1,280

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,280 $0 $1,280 $1,411 $1,411 $-131
 
Total* $1,280 $0 $1,280 $1,411 $1,411 $-131

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2013 

02/01/2013 
 

 
01/01/2013 

02/01/2013 
100  11/15/2012 

04/30/2013 


-3 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

02/28/2013 
 

 
11/01/2012 

02/28/2013 
100  11/15/2012 

04/30/2013 


-2 
Begin Right of Way Phase

End Right of Way Phase
 

02/15/2013 
 

 
 

02/15/2013 
100  11/15/2012 

04/30/2013 


-2 
Begin Construction Phase

End Construction Phase
04/01/2013 

07/01/2013 
 

 
04/01/2013 

07/01/2013 
100  07/15/2013 

04/22/2014 
-3 

-10 
Begin Closeout Phase

End Closeout Phase
07/01/2013 

09/01/2013 
 

 
07/01/2013 

09/01/2013 
100  04/23/2014 

08/11/2014 
-10 

-11 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$613,000
Current Approved:
$613,000
Actual Expenditures:
$613,000

 

Status as of December 31, 2023.