2013 STREET REHAB |
Description: Rehab Alhambra Drive and Alida Way
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | South San Francisco |
Zip Code | 94080 |
Senate District |
13 |
Assembly District | 22 |
Congressional District | 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of South San Francisco | Andy Tan | (650) 829-6667 | andy.tan@ssf.net | |
Design (PS&E) Phase |
City of South San Francisco | Andy Tan | (650) 829-6667 | andy.tan@ssf.net | |
Right of Way Phase |
|||||
Construction Phase |
|||||
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$502 | $0 | $502 | ||||
Non-bond Funding | |||||||
Local** |
$512 | $0 | $512 | ||||
Total**** | $1,014 | $0 | $1,014 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$10 | $0 | $10 | $10 | $10 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,004 | $0 | $1,004 | $1,393 | $1,393 | $-389 | |
Total* | $1,014 | $0 | $1,014 | $1,404 | $1,404 | $-389 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/22/2012 10/22/2012 |
|
10/22/2012 10/22/2012 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2012 03/01/2013 |
|
12/01/2012 03/01/2013 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2013 07/31/2013 |
|
05/01/2013 07/31/2013 |
100 | 08/26/2013 12/13/2013 |
-4 -4 |
Begin Closeout Phase
End Closeout Phase |
08/01/2013 08/31/2013 |
|
08/01/2013 08/31/2013 |
100 | 12/30/2013 07/31/2014 |
-5 -11 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$502,000 |
Current Approved: |
$502,000 |
Actual Expenditures: |
$502,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle